Mactan House, Amalie
Lot 16, Block 4, Vittoria Construction Notes
Last update: May 9, 2006
Previous: April 28, 2006
Previous: April 25, 2006
Previous: April 20, 2006
Pillars
Before the pillars go in check the orientation of the house with the
plan, the pillars are the small rectangles on the plan joining the
hollow block walls. The foundation of the pillars should be deep
and on solid ground. The pillar foundations are usually wider than the
pillar that is constructed on top. A minimum distance of 3 centimeters
should be kept between steel bars and outside wall of the pillar.
The concrete should be a clean pour with little or better no air
bubbles. The concrete must definitely not be brittle and crumble. If a
small air pocket has exposed some of the bar (say no more than 1 inch)
and the concrete is otherwise without flaw, get the hole filled up with
a strong (dark) cement repair. If the flaw is bigger or if the concrete
is of bad quality get them to knock it out and pour it again.
Walls
At regular intervals there should be steel reinforcements in the walls
(horizontal and vertical). This is called the Reinforced Hollow
Concrete Block Masonry (RHCBM) System for and makes for a seismic
resistant construction.
Make sure there is a horizontal reinforcement close to the top
layers of each
window as this is the weak point in a wall. Cracks will ofter form
above windows if the reinforcements have been forgotten. Ignore cracks
in plaster as plaster shrinks when it dries and this can be repaired,
instead check the hollow blocks and the cement for the cracks.
Cracks between the hollow block construction and the pillars are not
good and should be investigated and redone if necessary as they
probably mean the wall is not well connected to the pillar. We also
requested that all the walls (also between bedrooms) on the second
floor be hollow blocks. They will also carry the weight of people and
storage on the roof. These requirements may
change with the new contractor.
Concrete Floor
The gravel must be well compacted. The steel bars must be well below
the floor surface, again more than 3 centimeters if possible. Check the
pipes are not damaged and located below the steel bars before the
concrete is poured. Check the consistency of the poured concrete. It
must be flat, smooth and flawless. The same is true for the second
floor. If the concrete is unevenly poured tell the workers it is OK but
they have to even it out when the tiles are installed and warn them you
will not accept an uneven tiled floor. They can still make even tiles
on an uneven floor but it will mean extra work so watch on them!
Steel "rebars" are the most important
part of a concrete floor apart from the quality of the concrete mix.
They should be well anchored into to walls on all sides and well
embedded so that they do not touch the surface of the concrete floor.
They must be connected at short and regular intervals with twists of
plain steel wire. The same goes for the pillars. Do not accept any
pipes above the rebars as there would be no room for the concrete at
this place and this could cause cracks in the future.
Drains
Drains for the bathrooms are four. One for the toilet bowl and one for
the basin. One close to the corner for the shower cabinet. One in the
middle of the room for the drain. Make sure that the floor drain
will not be covered by the cabinet when it is installed. The cabinet is
an arc and needs over 70 centimeter radius. When Helen brings back the
copies I'll draw it on a plan and put a picture here.
Bathroom
Make sure the window is right next to the pillar and not in the middle
of the bathroom wall as it will otherwise interfere with the shower
cabinet wall. An electrical outlet (3pin) must be present for the
boiler on both floors. Check that the hole and pipe for this are there
before the tiles are installed, the outlets should be there when the
other outlets are also installed.
Electrical Pipes
Make sure at all times the pipes are not squashed, crushed or damaged
in any way as in the future wire may have to be redone or added. The
pipes should be clearly visible in their wall holes and clear of dirt.
Make sure the pipes are below the steel reinforcements before the
concrete floors are poured. All pipes leading to electrical outlets in
the walls should have 3 wires at the opening of the pipe (For Earth,
Live and Neutral). The four extra outlets for TV/Phone/Network should
each have two pipes that lead and meet above the bathroom on the second
floor, that makes eight pipes. We asked for an extra outlet above the
2nd floor bathroom, check at least the pipe with the three wires is
there (maybe there will therefore be nine pipes).
2nd floor celling / roof floor
Helen and I asked for the roof to be a storage area. The celling must
be reinforced, the metal frame will have to be a strong construction,
if necessary get the workers to walk and jump lightly on the structure
before the ceiling boards and the roof floor are installed. Movement in
the roof must not create cracks in the 2nd floor ceiling. The opening
in the bathroom should be at least 80 centimeters in both directions (1
meter is better), the roof is storage and adequate access will be
required. The floor of the roof will be made of non instect attackable
material (to be decided in the agreements, see link on top of page).
This material may have joins on the edges (Tongue and Grove for
example). If not and simple board shapes are used, then make sure the
joins happen above a support so that the boards do not give way when
stepping on the edges. Tongue and Grove systems should be strong enough
to have the joins anywhere. The edges of the entire floor should not
touch the house walls. A gap will ensure the floor can expand a bit
with temperature variations.
Tongue and Grove joins should be
strong enough not to need a support directly below the meeting point.
If the joins are straight with no locking between the elements, check
there is support below the point at which the two boards meet.
Water
We have asked for an extra outlet (bib) to be installed outside the
kitchen. Also on the inside there must be a tap or valve to turn of the
water outside.
Roof
I feel strongly that roof should be a solid construction as we will for
sure be using it extensively. Make sure not insect prone materials are
used as floor boards of the roof and that movement in the roof deos not
cause cracks in the plaster of the 2nd floor ceiling. When the boards
are in, clim into the roof and check the insulation. Make sure there
are not gaps in the
insulation. Insulation has no purpose if the air can blow between or
around it!
Tiles
Always be fussy about the tiles! Check each one by hitting it with a
solid piece of wood, if it cracks or sounds hollow have it replaced. Do
not accept wavy or uneven floors. Here in Europe the gaps between the
tiles are filled with a cement glue but not in the angles of the walls
as we fill these with silicone in case the walls move a bit. I do not
know in the Philippines. But if they use the cement glue in the angles
of the walls to fill the gaps between the tiles then this would be a
good place to look for cracks. This is especially serious in the
bathrooms as the water would get into the concrete and cause damage and
maybe fungus.
Thank you Norman and Fely for supervising all this, Ang higala sa
panahón sa kalisód mao’y higala nga tinood.